A setting in the Dates menu. When this is on, actual dates will be used to determine late dates, critical path, slack times, and resource durations. This toggles with Calculate Using Planned.
                     
A setting in the Dates menu. When this is on, planned dates will be used to determine late dates, critical path, slack times, and resource durations. This toggles with Calculate Using Actual.
               
-- part contents for card part 4
----- text -----
2 of 14
-- part contents for background part 35
----- text -----
         
An item of task information that can be displayed in the Schedule Chart or used as part of a search formula. Examples of attributes are dates, durations, slack times, and resource names.
        
A setting in the Dates menu. If AutoCalc is on, the schedule will be recalculated every time you enter or change an item of task information. Otherwise, you must choose Calculate Now to recalculate.